♫
Now Playing
Ambient Radio
♫

Keep Learning?

Sign in to continue practicing.

Three workers, P, Q, and R, can complete a certain task individually in 12 days, 15 days, and 20 days respectively. Initially, P and Q start working together on the task. After 4 days, P leaves the work, and R joins in his place. However, due to some initial acclimatization issues, R's efficiency is 25% less than his usual efficiency for the first 3 days he works. After these 3 days, R regains his full efficiency for the remainder of the task. Assuming work progresses continuously, what is the total number of days taken to complete the entire task? A) 7.5 days B) 7.75 days C) 8 days D) 8.25 days
The correct answer is **B) 7.75 days**. Let's break down the problem step-by-step to determine the total time taken. **Step 1: Calculate the total work and individual efficiencies.** To find a common unit for total work, we take the Least Common Multiple (LCM) of the number of days each person takes to complete the work. LCM(12, 15, 20) = 60 units. Now, we calculate the efficiency of each worker in units per day: * P's efficiency ($E_P$) = $\frac{\text{Total Work}}{\text{Days P takes}} = \frac{60}{12} = 5$ units/day. * Q's efficiency ($E_Q$) = $\frac{\text{Total Work}}{\text{Days Q takes}} = \frac{60}{15} = 4$ units/day. * R's efficiency ($E_R$) = $\frac{\text{Total Work}}{\text{Days R takes}} = \frac{60}{20} = 3$ units/day. **Step 2: Calculate work done in Stage 1.** Initially, P and Q work together for 4 days. * Combined efficiency of P and Q = $E_P + E_Q = 5 + 4 = 9$ units/day. * Work done in the first 4 days = $9 \times 4 = 36$ units. * Remaining work = $60 - 36 = 24$ units. **Step 3: Calculate work done in Stage 2 (R with reduced efficiency).** After 4 days, P leaves, and R joins. R's efficiency is 25% less for the first 3 days he works. * R's reduced efficiency ($E_{R_{reduced}}$) = $E_R \times (1 - 0.25) = 3 \times 0.75 = 2.25$ units/day. * The team now consists of Q and R (with reduced efficiency). * Combined efficiency of Q and (reduced) R = $E_Q + E_{R_{reduced}} = 4 + 2.25 = 6.25$ units/day. * They work for 3 days in this phase. * Work done in these 3 days = $6.25 \times 3 = 18.75$ units. * Remaining work = $24 - 18.75 = 5.25$ units. **Step 4: Calculate work done in Stage 3 (R with full efficiency).** After 3 days, R regains his full efficiency. The team still consists of Q and R. * Combined efficiency of Q and (full) R = $E_Q + E_R = 4 + 3 = 7$ units/day. * Time taken to complete the remaining $5.25$ units of work = $\frac{\text{Remaining Work}}{\text{Combined Efficiency}} = \frac{5.25}{7}$ days. * $\frac{5.25}{7} = \frac{525}{700} = \frac{21 \times 25}{28 \times 25} = \frac{21}{28} = \frac{3}{4} = 0.75$ days. **Step 5: Calculate the total time taken.** Total time = Time in Stage 1 + Time in Stage 2 + Time in Stage 3 Total time = $4 \text{ days} + 3 \text{ days} + 0.75 \text{ days} = 7.75$ days. Therefore, the entire task is completed in 7.75 days. **Why other options are incorrect:** * **A) 7.5 days:** This would imply either R's reduced efficiency phase was shorter or the remaining work was less, or the efficiencies were miscalculated. Our step-by-step calculation shows 7.75 days precisely. * **C) 8 days:** This would mean that the final stage took longer than 0.75 days, which is not consistent with the remaining work and full efficiencies. * **D) 8.25 days:** This is a higher value and would result from errors in calculation, potentially overestimating the time taken in one or more stages. The detailed calculation confirms that 7.75 days is the precise answer.
100%